Moree Plains Shire Council resolved at its extraordinary meeting, held on October 12, to award the tender for the construction of the 50-metre pool at the Moree Artesian Aquatic Centre (MAAC) to Crystal Pools Pty Limited.
Crystal Pools Pty Ltd is a leading Australian commercial pool builder, owned and operated since 1957.
Having been in the business for over 65 years, they are certified for federal, state and local government commercial swimming pool design and construction, making them familiar with regulations and requirements, council said in a statement.
“My fellow councillors and I are very excited to have secured a reputable company to complete the 50-metre pool for the community and our visitors, as we are all aware the artesian water brings tourism to our shire,” Mayor Mark Johnson said.
“To have the centre completed with its cold-water pool, will help us reinstate us as the ‘Artesian Capital’. We understand the frustration this process has caused in the community, however, we needed to ensure our due diligence was done regarding this project.
“The awarding of the tender today marks a significant step forward to returning this iconic asset to our shire.”
In its aquatic centre update, council also provided a timeline of redevelopment works.
Current/October 2023:
– All pools at the MAAC are currently closed. Belgravia Leisure remains operating the centre to allow customers access to the gym and café and to assist patrons with any enquiries.
– Tenders for the club house and grandstand are open for a further two weeks.
November 2023
– The Program and Passive Pools will re-open.
– The ‘Learn to Swim’ Program will recommence.
– Les Mills Virtual Program will be introduced at the gym, these virtual programs will add to group exercise in cinematic-quality classes from some of the world’s best instructors.
– New additions and refreshed painting to the function area.
December 2023
– Mid- December – re-opening of the Wellness Centre.
– Waterslide summer hours recommence, 3pm to 6pm.
January 2024
– Mid-January – Active Pool reopening.
– Gym flooring and equipment upgrades to commence.
– Mid-January – Earthworks to commence bulk excavation where the previous 50-metre pool was, with piling and back filling.
April 2024
– Construction of the 50-metre pool will commence, with a build time of approximately 15 months.