The new Violet Street Bridge is moving closer to reopening, with construction of the bridge deck and shared pathways now complete.
Narrabri Shire Council has reached a major milestone on the $7.5m replacement project, with pavement works on both approaches also progressing despite recent wet weather.
Narrabri Shire mayor Darrell Tiemens said completion of the bridge deck, including the shared pathways, was a significant achievement.
“The completion of the bridge deck and shared pathways is a major milestone and a clear sign of the progress being made towards completion of the new bridge,” Cr Tiemens said.
“Despite recent wet weather, the contractors are making great headway. It’s fantastic to see how far the project has come and the new bridge taking shape as we move closer to completion.”
Works are now focused on the installation of new kerb and gutter, along with final finishing works on the bridge’s supporting concrete structures.
The next stage will include completing the upgraded 300mm water main, installing bridge barriers and overhead street lighting, and constructing a pedestrian refuge on the Selina Street approach.
Pavement works on both approaches will also be completed, along with shared pathways linking the bridge to the existing network, before bitumen sealing and line marking.
Cr Tiemens said the new bridge would provide significant improvements for motorists, pedestrians and the wider community.
“This bridge will be a significant upgrade,” he said.
“It can take heavy vehicles, so if there is an issue with the Narrabri Creek Bridge, there is an alternate route for trucks.
“It also has footpaths on both sides for safe pedestrian access, and the barriers can be removed more quickly, meaning the bridge can stay open for longer and reopen sooner during flood events.”
Cr Tiemens acknowledged community frustration over delays and thanked residents, businesses, staff and contractors for their patience and efforts.
“I know our community has been frustrated by the delays involved with this project, so have I, and I think nearly everyone involved,” he said.
“I would like to thank the community for their patience and understanding, plus the staff and contractors who have pivoted and worked tirelessly to minimise the delays as much as possible – I am really looking forward to opening this bridge soon.”
While recent rain has affected progress on the approaches, the project is expected to reach practical completion in late November or early December, subject to unforeseen delays.
The $7.5m project has received $5m through the Infrastructure Betterment Program, jointly funded by the Australian and NSW governments under the Disaster Recovery Funding Arrangements.
The remaining $2.5m was contributed through the federal government’s Roads to Recovery Program.
More information about the project is available through Narrabri Shire Council’s website.