Violet Street bridge upgrade budget amended
Narrabri Shire Council has adopted an amended budget for the $7m replacement of the Violet Street bridge following a project delay. The council had previously announced the completion of the bridge would be delayed after piling works had taken longer than anticipated. Variations to the project has meant that additional costs will come from a $400,000 contingency allocated towards the project. At last week’s meeting, councillors were informed that the contractor had been on-site for eight weeks longer than expected with the variation for time and costs amounting to $498,131. The last pile for the foundations was driven on 23 […]